Charges for installation Environmental Permits

You need to pay a charge when you apply for a new installations Environmental Permit, or if you want to make a change to your permit, transfer or surrender it.

There is also an annual charge to cover compliance costs.

There are two types of charges - variable for complex applications, and fixed for simpler, lower risk applications.

Find out whether you qualify for a low impact Environmental Permit

Charging tool for complex permit applications

You can use the charging tool to work out the cost for all the activities in your application.

Use the charging tool for a new application

Use the charging tool to vary a permit

Use the charging tool to surrender a permit

Use the charging tool to transfer a permit

The application charges for an administrative variation, a minor technical variation, a full transfer and a low risk surrender are the same for all applications.

You do not need to use the charge tool for these.

Annual charge (known as subsistence)

There is a fixed annual charge for the following activities:

  • Low impact installation - £563
  • Standalone landfill gas engine - £3670
  • Intensive farming installation - £1119 (accredited) or £2669 (non-accredited)
  • Directly associated activity - £3670
  • Hydrogen production by electrolysis of water (small scale) - £920
  • Anaerobic digestion - £2194

Annual charges for complex permits are based on operational risks.

Complete our Operational Risk Assessment (OPRA) spreadsheet to work out how much you will be charged.

You will need to complete the OPRA spreadsheet annually.

Complex installation permits

Application charges depend on the scale, complexity and number of activities of your operation.

Complex permits fall into four bands depending on the degree of complexity of your operation. In general, if you are carrying out:

  • less than three activities, you should qualify for band 1
  • 3 to 6 activities will most likely put you in band 2
  • more than 6 activities will be a band 3 bespoke permit
  • additional complexity may be band 4.

Please complete the charging tool to find out the exact cost, including all factors.

Band 1 installation permit

New application: £13609

Vary an existing permit: £613 (administrative), £2693 (minor technical), £8967 (normal), £13035 (substantial)

Transfer your permit: £5238 (partial), £2680 (full)

Surrender your permit: £6692 (partial), £5812 (full)

Low risk surrender: £2693

Surrender of a site that has never operated: £1218

Band 2 installation permit

New application: £20470

Vary an existing permit: £613 (administrative), £2693 (minor technical), £11413 (normal), £19635 (substantial)

Transfer your permit: £7243 (partial), £2680 (full)

Surrender your permit: £9166 (partial), £8369 (full)

Low risk surrender: £2693

Surrender of a site that has never operated: £1218

Band 3 Bespoke installation permit

New application: £32718

Vary an existing permit: £613 (administrative), £2693 (minor technical), £19580 (normal), £31395 (substantial)

Transfer your permit: £11842 (partial), £2680 (full)

Surrender your permit: £18349 (partial), £14731 (full)

Low risk surrender: £2693

Surrender of a site that has never operated: £1218

Band 4 Bespoke installation permit

New application: £44850

Vary an existing permit: £613 (administrative), £2693 (minor technical), £35132 (normal), £42687 (substantial)

Transfer your permit: £14638 (partial), £2680 (full)

Surrender your permit: £24297 (partial), £20559 (full)

Low risk surrender: £2693

Surrender of a site that has never operated: £1218

Medium combustion plant activities on installations

If you have a medium combustion plant attached to your installation, you will be charged for these additional activities.

New application: £1626

Vary an existing permit: £976

Transfer your permit: No additional charge

Surrender your permit: £976

Local authority activity (Part A2 or Part B activity) on installations

If you have a Part A(2) or Part B activity on your installation, you will be charged these additional activities:

New application: £1626

Vary an existing permit: £995

Transfer your permit: No additional charge

Surrender your permit: £976

Waste activities on an installation

If you carry out waste activities on your installation, you will be charged 20% of the standalone charge for a waste permit.

New application: £1943

Vary an existing permit: £1613

Transfer your permit: No additional charge

Surrender your permit: No additional charge

Additional assessments

As part of your application for an installation permit, you’ll carry out a screening exercise. Depending on the results of the screening, you may need to carry out one of the further assessments below.

Full air quality modelling assessment: £2692

Fugitive emissions assessment: £1657

Odour assessment: £1619

Bioaerosol modelling assessment: £3380

Full noise modelling impact assessment: £2425

Fire prevention and mitigation plan: £2343

Deposit for recovery assessment: £1734

Water Framework Directive assessment of process effluent: £3222

Application charges for lower risk installations

Low Impact standard rules permits (SR2009 no.2)

New application: £4429

Vary an existing permit: £613

Transfer your permit: £2100 (partial or full transfer)

Surrender your permit: £258 (partial or full surrender)

Standard rules for anaerobic digestion

New application: £4646

Vary an existing permit: £613

Transfer your permit: £2100 (partial or full transfer)

Surrender your permit: £258 (partial or full surrender)

Standalone landfill gas engine

New application: £12989

Vary an existing permit: £613 (administrative), £1891 (minor technical), £7916 (normal), £11683 (substantial)

Transfer your permit: £3996 (partial), £2533 (full transfer)

Surrender your permit: £2533 (partial), £1774 (full surrender)

Bespoke permit for low impact installations

New application: £7278

Vary an existing permit: £613 (administrative), £1035 (minor technical), £4424 (normal), £6544 (substantial)

Transfer your permit: £3996 (partial), £2533 (full)

Surrender your permit: £2533 (partial), £1774 (full)

Intensive farming installation

New application: £9549

Vary an existing permit: £613 (administrative), £2693 (minor technical), £5841 (normal), £7639 (substantial)

Transfer your permit: £2680 (partial or full transfer)

Surrender your permit: £5812 (partial or full surrender)

Small scale hydrogen production

New application: £788

Directly associated activities

Activities which are part of an installation but are carried out by an independent company may need a directly associated activities permit.

New application: £7983

Vary an existing permit: £613 (administrative), £1140 (minor technical), £4856 (normal), £7178 (substantial)

Transfer your permit: £3996 (partial), £2533 (full)

Surrender your permit: £2533 (partial), £1774 (full)